ADDITIONS/GARAGES: B Footing, B Backfill, B Slab, B Framing, B Sheathing, E Rough, P Rough (If Installed) B, Insulation, B, E, P, F Final
BACKFLOW PREVENTER: P Final (Inside of House)
BASEMENT: B Framing, E Rough, P Rough (If Installing ) B Insulation (If Installing) B, E, P, F Final
DECK: B Footing, B Framing , B Final
FENCE: B Final
FURNACE: B, E, F, P Final
GAS LOG SET: P Gas Test, B, P Final
HOT TUB: B, E Final
POOL INGROUND: B Footing, B Collar, B Steel, E Trench, E Bonding, P Gas Pipe (If there is a heater) B, E, P Final - Call Engineering for Final Grading 799-9396
RADON: B, E Final
ROOF & SIDING: B Final
SEWER CONNECTION: P Trench, P Final
SHED: Under 200sq. ft. B Final, Over 200sq. ft. B Footing B Final
SIGNAGE: B Footing (If Required) B, E Final
SINGLE FAMILY DWELLING: B Footing, B Foundation, B Backfill (need location survey), P Sewer & Water Service, B Basement Slab, B Garage Slab, P Gaspipe, B Framing, B Sheathing , E Rough, P Rough, B Insulation, B, E, P , F Final
TANK: Underground Storage B Rough and Final (Tank out of ground, hole open ) Oil Tank Placement B, F, P, Final
WATER CONNECTION: P Trench, P Final |